The Correct Order of Finishing Works — Modern Sequence

For a high-quality home-finishing project, work must follow the right sequence so one job doesn't damage another. Here's the modern 16-step order we follow at Besufkad.

The Correct Order of Finishing Works — Modern Sequence
  1. 1. Wall inspection & preparation

    • Seal any cracks in the walls.
    • Straighten uneven walls and edges.
    • Clean the entire building.
  2. 2. Plumbing (rough-in)

    • Install water supply pipes.
    • Install drainage pipes.
    • Install toilet & bathroom plumbing.
    • Pressure-test all water lines before closing walls.
  3. 3. Electrical (first fix)

    • Install conduits, back-boxes and breaker box.
    • Pull wiring where appropriate.
    • Run internet, TV and security-camera lines.
  4. 4. Gypsum board work

    • Install Chinese or local gypsum board.
    • Prepare lighting positions.
  5. 5. Wall skim (chuck / putty)

    • Chuck for interior walls.
    • Putty for exterior walls.
    • Allow proper drying time.
  6. 6. Floor screed

    • Let it dry completely.
  7. 7. Waterproofing

    • Bathrooms.
    • Toilets.
    • Balconies.
    • Kitchens (if needed).
    • Water tanks.
  8. 8. Wall ceramic work

    • Bathroom walls.
    • Kitchen walls.
    • Exterior walls as needed.
  9. 9. Floor tiles / ceramic

    • Living room.
    • Bedrooms.
    • Kitchen.
    • Bathrooms.
    • Corridors.
  10. 10. Painting

    • Primer.
    • First coat.
    • Second coat.
    • Final finish coat.
  11. 11. Doors & windows

    • Install doors.
    • Install locks.
    • Install windows.
    • Install glass.
  12. 12. Electrical (second fix)

    • Switches.
    • Sockets.
    • Breakers.
    • Light fixtures.
  13. 13. Plumbing (second fix)

    • Toilets.
    • Basins.
    • Shower drains.
    • Kitchen sink.
    • Water heater install.
  14. 14. Kitchen cabinets & wardrobes

    • Install cabinets.
    • Install wardrobes.
  15. 15. Final cleaning

    • Clean paint drips off floors.
    • Clean doors and windows.
  16. 16. Final testing & handover

    • Test electrical.
    • Test plumbing lines.
    • Inspect paint.
    • Check doors and windows.
    • Fix any defects before handover.

Following this sequence helps you avoid re-doing work. This is how Besufkad Finishing delivers — you deserve a premium life.